Jackson & Associates | Banking Disputes | Commercial Law

(02) 8076 6020

  • Home
  • Services
  • Our Team
    • Peter Jackson
    • Costin Stan
    • Jason Tran
  • Newsletters
  • Contact
  • Home
  • Services
  • Our Team
    • Peter Jackson
    • Costin Stan
    • Jason Tran
  • Newsletters
  • Contact

September 2020

The construction industry and a new duty of care …

It is well understood that the Home Building Act 1989 NSW (Home Building Act) provides that the building work “be done with due care and in accordance with the plans and specifications in the contract”. Under the Home Building Act, claims for major defects must be made within six years of the completion of the work and two years in other cases. If the builder wishes to join others in any claim it is his obligation to do so.

In June 2020, the Design and Building Practitioners Act 2020 NSW (Design and Building Act) commenced. This act imposes a range of additional statutory obligations on builders, architects, engineers and others working in the building industry. Furthermore, this act was introduced because although the Home Building Act imposed statutory warranties, there was doubt that a duty of care existed and this act changes that position. Section 37(1) of the Design and Building Act stipulates that:

A person who carries out construction work has a duty to exercise reasonable care to avoid economic loss caused by defects —

(a) in or related to a building for which the work is done, and

(b) arising from the construction work.

The new law provides that claims can be made for six years from when the loss becomes apparent or for up to ten years after the work was completed and with no distinction between major and minor defects. Moreover, the new duty of care is retrospective and extends back as far back as ten years. If the claimant considers others should share the responsibility for the loss they must be joined in the claim by the claimant. This is a different approach to that taken in claims commenced under the Home Building Act.

This is important legislation that will benefit those who wish to claim loss for defective building work because they were unable to establish a duty of care or who missed the limitation period in the Home Building Act.

Should any of newsletter readers find themselves in such a scenario they should contact Peter Jackson at pjackson@jacksonassoc.com.au or Costin Stan at cstan@jacksonsasoc.com.au.

The COVID19 pandemic and force majeure clauses in contracts ….

A force majeure clause in a contract relieves the affected party from performing the obligations set out in the contract because the event is outside of the reasonable control of that party.

In Australia, force majeure is recognised as a contractual obligation and does not form part of the common law. This means that the terms of the force majeure clause in a contract are negotiated between the parties. Common events that permit a party to terminate a contract include but are not limited to “acts of God“, “natural disasters“ and “acts of war“.

If a new contract is being negotiated, parties should be prudent and negotiate the introduction of an additional event such as “global pandemic“.

In existing contracts, the force majeure clause should be examined to determine if the clause applies to the present COVID19 pandemic circumstances.

Contact Us

Level 13, 111 Elizabeth Street
Sydney NSW 2000
T: (02) 8076 6020

Peter Jackson
pjackson@jacksonassoc.com.au

Costin Stan
cstan@jacksonassoc.com.au

Testimonials

Thank you for all your advice, knowledge and dedication in assisting me...

Louie A, 23/7/20


Thank you also for the compassion you had shown me through that difficult time and I have always had a good experience when dealing with your company...

I would never hesitate to sing your praises and if needed use your services in the future...

Marc P, 20/7/20

Read More Testimonials

To Subscribe to our Newsletter, please enter your email address below.

Newsletter

  • February 2021
  • January 2021
  • December 2020
  • November 2020
  • October 2020
  • September 2020
  • August 2020
  • July 2020
  • June 2020
  • May 2020
  • April 2020
  • March 2020

Jackson & Associates, Solicitors

The firm works to achieve the best possible result for the client. We bring experience,hard work and clear planning at a fee negotiated with the client, without compromising professional standards.

We offer

Expertise and experience
Responsiveness to client needs
Flexible charging policies

Connect with us

  • Email
  • Facebook
  • LinkedIn

Copyright © 2019